FSV - Project Update  
   
         
 
     
 
ABOUT FSV
 

 
     

 
 
Facility
Status
Fence  100% Done
Survey All sold plots have been surveyed
Drainage 100% done
Land scaping Front Entrance of Estate:100% Done
Recreational Park1: 100% Done
Recreational Park2: 100% Done
Private Development 8 houses are at different stages of construction
Water The central water treatment plant is now fully operational,  next stage is running the piping to all the plots
Access Road 100% done